Texas counted 410 GW of power requests. Most had no grid study.

Section 1 of 9 · Introduction

CASE 039 · AI DATA CENTRES / THE GRID

Texas counted 410 GW of power requests. Most had no grid study.

An announcement can reserve a headline. A connection request can reserve a place in line. Neither turns on a server. Texas’s grid operator put the difference on a slide: roughly 410 gigawatts of proposed large loads, with most of its 2030 projection in the category “No Studies Submitted”. The industry sells the future in buildings; the grid has to find the power in the present. [1]

Prepared
13 November 2026
Scope
Texas grid requests, verification, power and financing

Estimated reading time · 5 min

ERCOT slide of large-load requests as of 26 March 2026, separating no-study, under-review, approved, not-operational and energised capacity.
ERCOT presentation to the Texas House Business & Commerce Committee, 1 April 2026, slide 3. The 2030 bar is a projection of proposed load, not an inventory of operating data centres. Read the original presentation · View the slide. [1]

The Electric Reliability Council of Texas (ERCOT), which operates most of the state’s electricity grid, tracked approximately 410 GW of large loads seeking connection in March 2026, about 87% of them data centres. In its chart of projected load by 2030, 410,618 MW is the total. Of that, 293,651 MW sits under “No Studies Submitted”: about 72% of the projected total. Only 5,778 MW is classified “Observed Energized” on that bar. These are status categories in a planning chart, not a count of cancelled projects or a prediction that the other 405 GW will never operate. [1]

By June ERCOT said it was tracking more than 438 GW of large-load requests, nearly 89% from data centres. It approved a batch process to test which large users could connect, where, and what upgrades the grid would need. In August the Texas governor ordered verification before data-centre loads advanced; ERCOT issued requests for proof in September. The authority responsible for connecting the projects had moved from counting requests to interrogating them. [2, 3]

A developer may ask more than one utility about possible sites before choosing one. FERC commissioner David Rosner warned that speculative requests can clog studies, distort demand forecasts and model projects that never materialise. In PJM’s region, the operator now asks whether a customer has duplicated a request elsewhere and treats near-term projects differently when they lack firm commitments. PJM explicitly says it has no load interconnection queue: it receives large-load forecast adjustments from utilities. The mechanisms differ; the danger of counting the same future twice does not. [4, 5]

ERCOT’s November preliminary audit gives a narrower view than the headline 438 GW queue. It sent a community-impact questionnaire to 465 identified loads and received 433 responses covering about 177 GW of requested capacity. All 245 loads at or above 75 MW responded. Later planned opening dates had more “not applicable or unable to answer” responses, consistent with less mature plans. The 177 GW describes this questionnaire’s population; subtracting it from 438 GW as if the rest had vanished would be false. ERCOT plans a final analysis in December. [6]

Even a serious developer needs a site, permits, transmission, generating capacity, equipment, cooling and financing on compatible dates. The US Department of Energy says additional transmission is urgently needed to accommodate new generation and large loads. A request to draw electricity is not a contract for a power plant, nor is a power plant automatically connected to the warehouse that needs it. The mismatch can delay both the opening and the revenue that was meant to pay for construction. [7]

Project Jupiter in New Mexico makes the chain visible. Reuters reported in September that Oracle gave Blue Owl’s developer a force-majeure notice over possible delays securing power for a campus intended to support OpenAI. A source told Reuters Oracle remained bound to the lease but sought to defer higher payments if the project missed its planned 2028 opening. Oracle said the project remained on its planned schedule, and Blue Owl said the notice did not change financial commitments. The notice is evidence of a risk being allocated in a contract, not proof that Jupiter has been abandoned. [8]

Some data centres are being built and some operate. A failed negotiation for one tenant can leave a viable project for another: Reuters reported that Microsoft agreed to take a roughly 700 MW Abilene development after Oracle and OpenAI withdrew from talks, while their existing Stargate agreements remained unchanged. Oracle disputed that planned capacity at the original Abilene campus was delayed. An expansion changing customer is not the same as the entire site disappearing. [9]

Large requests can be earnest even before every study is complete. Screening them more rigorously may reduce inflated forecasts while delaying legitimate projects. The fair test is to follow each proposal from load request to service agreement, construction, energisation and actual use. This record establishes a large gap between stages. It cannot assign a single failure rate to all announced AI facilities or predict how many Texas projects will open.

ERCOT’s own colours tell the story. On the slide, the tallest part of the future is a category that had not submitted a study. The later audit asks developers to name their power, water, cooling, ownership and public benefits. When a planned campus is described as capacity already secured, ask which stage it has actually reached and who pays if the line to the socket arrives after the bill. [1, 6]

  1. Does the named project control its site, hold permits and have a signed electricity-service agreement?
  2. How much of the announced capacity is energised now, and how much exists only in a forecast or request?
  3. Who funds grid upgrades and bears the cost if the customer, opening date or power demand changes?

The queue is full of megawatts. A server cannot run on a place in line.

Sources

  1. ERCOT, large-load update, 1 April 2026, especially slide 3: status categories and projected load by 2030.
  2. ERCOT and PUCT, Batch Zero announcement, 18 June 2026: 438 GW requests, data-centre share and batch-study method.
  3. ERCOT, Batch Zero verification notice, 9 September 2026: state-directed audit before projects advance.
  4. FERC commissioner David Rosner, remarks, 18 June 2026: speculative requests, duplicate forecasts and readiness requirements.
  5. PJM, large-load vetting update, 29 September 2026: firm commitments, duplicate inquiries and its distinct forecast-adjustment process.
  6. ERCOT, preliminary community-impact RFI summary, 5 November 2026: 465 requests, 433 responses, 177 GW questionnaire coverage and maturity caveats.
  7. US Department of Energy, draft National Transmission Needs Study, 2026: transmission constraints for new load and generation.
  8. Reuters, 24 September 2026: Oracle’s notice, power risk, project schedule and Blue Owl’s response.
  9. Reuters, 24 March 2026: changed tenant for a proposed Abilene development and the parties’ responses.
Evidence scopeGRID PRESENTATION / AUDIT / PROJECT CONTRACT
Current revision1.0 · 13 NOV 2026

The lead image reproduces ERCOT’s actual slide. Its figures are status categories for projected load. The November questionnaire covers a different subset of requests and is not presented as queue attrition. Project Jupiter’s schedule remains contested. The archive thumbnail is a conceptual illustration.